HAUSE SEWER NETWORKsewers@hause.ca403-679-3100
HAUSECalgarySewers.ca
System guide

Calgary's three wastewater treatment plants, measured: flows, process and published results

Calgary's Bonnybrook, Fish Creek and Pine Creek treatment plants compared with City data: daily flows since 2008, what each stage removes and the upgrades.

Conceptual illustration of screening · treatment tanks · final effluent
Illustrated field guideScreening · Treatment tanks · Final effluentConceptual subject study · not a surveyed layout or field measurement
Short answer

Calgary treats its wastewater at three City plants: Bonnybrook, Pine Creek and Fish Creek. The City's effluent data show Bonnybrook releasing about 405,000 cubic metres of treated water a day in 2025, roughly four-fifths of the total, with Pine Creek near 82,000 and Fish Creek near 28,000. Each plant screens, settles, biologically treats and UV-disinfects the flow before it reaches the Bow River.

Key takeaways
  • Averaged over 2025, the three plants released about 515,000 m³ of treated water a day; Bonnybrook alone accounted for about 79%.
  • Pine Creek's effluent records begin in July 2008; since then Fish Creek's average flow has fallen from about 65,000 m³ a day to about 28,000.
  • Plant flows peak on wet summer days, when rain and groundwater leak into sanitary pipes; Bonnybrook reached about 720,000 m³ on 22 July 2025.
  • Each treatment stage maps to a parameter the City reports: suspended solids, biochemical oxygen demand, ammonia, phosphorus and, after UV, fecal coliforms.
  • The City says Fish Creek can run at only about 30% of its capacity today; its upgrade is scheduled to finish at the end of 2031.
Fats, oils and grease building up in a drainFour stages of FOG buildup: warm liquid, cooling and clinging to the pipe crown and waterline, hardening into soap-like deposits, and finally a choked bore where solids snag.WARM FOG POUREDFlows awayCOOLS + CLINGSCoats the wallsHARDENSSoap-like layersCHOKED BORESolids snagMONTHS TO YEARS
Fig. 1Fats, oils and grease build up over months to years, then catch solids.

01 /Which plants treat Calgary's wastewater, and how much does each handle?

Three City plants take everything Calgary's sanitary system collects. The City's homeowner guide to the wastewater system names them, Bonnybrook, Fish Creek and Pine Creek, and the City's wastewater page says that together they meet the needs of more than one million Calgarians every day. The City's open data on treated effluent show how unevenly that work is shared.

Average daily effluent flow to the river by plant, selected years (City of Calgary open data, Wastewater Treatment Plants Effluent Water Quality; this site's calculation)
YearBonnybrookPine CreekFish Creek
2008About 376,000 m³Records begin July 2008About 65,000 m³
2012About 364,000 m³About 71,000 m³About 33,000 m³
2016About 323,000 m³About 84,000 m³About 36,000 m³
2020About 344,000 m³About 87,000 m³About 31,000 m³
2024About 371,000 m³About 74,000 m³About 28,000 m³
2025About 405,000 m³About 82,000 m³About 28,000 m³

Bonnybrook dominates in every year. In 2025 it carried about 79% of the three-plant total, Pine Creek about 16% and Fish Creek about 5%. A cubic metre is 1,000 litres, so an average 2025 day returned roughly 515 million litres of treated water to the river. The City's Fish Creek project page lists some of the south Calgary communities that plant serves: Deer Ridge, Deer Run, McKenzie Lake, Parkland and surrounding neighbourhoods.

02 /How do plant flows change through the year?

They rise when it rains, even though Calgary's sanitary and storm systems are separate. In January and February 2025, Bonnybrook averaged about 371,000 m³ a day. Its highest days that year all fell in late June and July, topping out at about 720,000 m³ on 22 July and about 717,000 m³ on 21 June. Pine Creek's busiest 2025 day, about 198,000 m³, was more than double its annual average.

People do not flush twice as much in July. The extra volume is water that reached the sanitary system through defects and improper connections: cracked service lines and joints, loose manhole lids in flooded streets, and yard drains or sump pumps tied into the sanitary side. Engineers call it inflow and infiltration. Part of it enters through private service lines, which is one reason a cracked lateral is a public problem as well as a private one. The mechanism is covered in sanitary vs storm sewers in Calgary.

The City has also published in-pipe measurements. Its Collection System Levels and Flows dataset holds seasonal readings, typically May to September, from flow meters in the sanitary system between 2005 and 2013. Both datasets are described in Calgary wastewater data and monitoring.

03 /What does each treatment stage remove, and how is it measured?

Treatment is a sequence of separations, and the City's effluent results track what each separation leaves behind. The stage descriptions below follow the City's homeowner guide; the right-hand column links each stage to the parameters in the City's published data.

Treatment stages and the effluent parameters that reflect them
Stage (City homeowner guide)What it removes or changesRelated parameter in the City's effluent data
Headworks: screens and grit tanksRags, wipes, plastics, toys, sticks and heavy grit, sent to landfillNot measured in effluent; protects the stages downstream
Primary clarifiers (about three hours)Settleable solids sink as sludge; fats, oils and grease are skimmed offTotal suspended solids
BioreactorsMicro-organisms with added air consume organic matter and nutrients such as ammonia and phosphorusBiochemical oxygen demand, ammonia, nitrogen species, total phosphorus
Secondary clarifiersMicro-organisms settle out; some return to the bioreactorsTotal suspended solids
Cloth disk filters (at some plants)Further solids, phosphorus and algaeTotal suspended solids, total phosphorus
UV disinfectionUltraviolet light alters microbes' DNA so they cannot reproduceFecal coliforms at the after-UV sampling sites

Averaged over 2025, the City's data show total phosphorus of about 0.21 mg/L at Pine Creek and about 0.5 mg/L at Bonnybrook and Fish Creek, and carbonaceous biochemical oxygen demand of about 2.5 mg/L at Pine Creek, 3.4 at Bonnybrook and 8.0 at Fish Creek. Plants differ in design and approvals, so compare each with its own history rather than ranking them. The City's guide says its laboratories sample every stage, every day of the year, to meet provincial standards.

Fats, oils and grease building up in a drainFour stages of FOG buildup: warm liquid, cooling and clinging to the pipe crown and waterline, hardening into soap-like deposits, and finally a choked bore where solids snag.WARM FOG POUREDFlows awayCOOLS + CLINGSCoats the wallsHARDENSSoap-like layersCHOKED BORESolids snagMONTHS TO YEARS
Fig. 2Grease narrows a pipe in stages until solids catch. The primary clarifiers skim fats off at the plant, but most grease problems happen long before, in house service lines and City mains.

04 /What happens to the solids and the energy they contain?

Sludge from the clarifiers becomes a resource. According to the City's homeowner guide, it is thickened, partly fermented to feed the bioreactors, and then digested in warm, oxygen-free tanks for about 25 days. Digestion converts organic matter into water, methane and carbon dioxide, and the City uses the methane as fuel for heat and electricity at its plants.

Where Calgary's biosolids go, by season (City homeowner guide)
SeasonRouteDurationEnd use
Spring and summerShepard LagoonsAbout six weeks of settlingApplied to farmland through the Calgro program
Fall and winterDewatering facility at Bonnybrook, then compostingAbout 60 days of compostingCategory A compost

The City says Calgro, which has run for more than 30 years, supplies nutrients for crops such as cereal grains, trees, sod, small oilseeds and dried legumes, and that the water pressed out during dewatering returns to the start of treatment.

05 /How are the plants being upgraded?

The biggest published change is at Fish Creek. The City's project page states that the plant can currently run at only about 30 per cent of its capacity, and that the upgrade will let it run safely at full capacity, improve treatment for regulatory compliance and add odour control. The page also estimates odour levels about five times lower at the plant boundary and three times lower at the nearest homes once work is complete.

Fish Creek Wastewater Treatment Plant upgrade schedule, as published by the City
PhaseTiming
Design2023 to 2026
Construction2025 to 2030
CompletionEnd of 2031

Schedules for projects this size move, so check the City's page for the current plan. Odour from the plants, and the biofilters planned at Fish Creek, are discussed in sewer smells in Calgary. The flow table above is a useful companion: as Fish Creek's capacity returns, its share of the south's flow may change, and the effluent data will show it.

06 /Why does the treatment plant matter to a homeowner?

Because the plant only sees what survives the trip, and your service line is the first part of that trip. Under the ownership split the City publishes, the street-side length of each connection is municipal and the house-side length is yours. A private line that leaks lets groundwater in, adding to wet-weather flows at the plant, and a private line that clogs backs sewage into a basement before anything reaches treatment. Bonnybrook also receives flow from neighbouring municipalities, including Airdrie, whose new connection is described in the Airdrie–Calgary wastewater pipeline. What happened when a pipe carrying raw sewage to Bonnybrook failed under the river in 2025 is covered in sewage leaks and the Bow River.

  • Toilets: the City's rule is pee, poo and toilet paper only; wipes, floss and hygiene products go in the garbage.
  • Kitchens: fats, oils and grease go in the green cart.
  • Medicines: return them to a pharmacy.
  • Your line: know what the City recorded for your connection with the Service Line Lookup, and see the full path in how Calgary's sewer system works.

For practical help when something backs up, CalgarySewers.com is this network's Calgary help desk. If you want your own line inspected, request quotes.

FAQQuestions people ask

How many wastewater treatment plants does Calgary have?

Three: Bonnybrook, Fish Creek and Pine Creek. The City says together they meet the wastewater needs of more than one million Calgarians each day.

Which is Calgary's largest wastewater treatment plant?

Bonnybrook, on the City's own effluent data: about 405,000 cubic metres a day on average in 2025, roughly 79% of the three-plant total.

Where does Calgary's treated wastewater go?

Into the Bow River, after ultraviolet disinfection. The City says it samples at all stages of treatment to meet standards set by the provincial government.

Why do Calgary's treatment plant flows rise in summer?

Rain and groundwater enter sanitary pipes through cracks, open joints, loose lids and improper connections. Bonnybrook's highest 2025 flows came in late June and July, close to double its winter average.

Is the Fish Creek treatment plant being upgraded?

Yes. The City says the plant can currently run at only about 30% of its capacity and lists design from 2023 to 2026, construction from 2025 to 2030 and completion at the end of 2031.

NETWORKGo deeper across the HAUSE Sewer network

Keep reading

Related guides

Conceptual illustration of house lateral · public main · treatmentSystem

How Calgary's sanitary sewer system works, from your floor drain to the Bow River

What a sanitary sewer is and how Calgary's works: service lines, mains, pump stations and three treatment plants, with numbers from the City's own records.

7 min read
Conceptual illustration of flow sample · treatment result · published recordData

Calgary wastewater data: treatment results, flows and virus monitoring, and how to read them

Calgary wastewater data explained: City effluent quality and flow records, COVID, flu and RSV wastewater monitoring, and sewer service line records.

6 min read
Conceptual illustration of sanitary to treatment · storm to drainage · separate routesSystem

Sanitary vs storm sewers in Calgary: two pipe systems, two destinations

Calgary's sanitary and storm sewers compared: where each goes, what may enter, design depths, ponds and outfalls, and why storms still cause basement backups.

7 min read
Conceptual illustration of observed problem · 311 report · city responseCivics

Calgary sewer bylaws and 311: what the rules cover and how to report a problem

Calgary's Wastewater Bylaw 14M2012, the Stormwater Bylaw and related rules in plain language, plus how to report sewer problems to 311 so they get acted on.

7 min read
Conceptual illustration of records · ownership · service callsReference

Calgary sewer questions, answered from the City's own records and rules

Answers to common questions about Calgary's sewers: who owns the line, what the City's records mean, where sewage goes, sewer depth, maps, bylaws and 311.

7 min read
Conceptual illustration of upstream community · transfer pipeline · treatment destinationSystem

The Airdrie–Calgary wastewater pipeline, and how Calgary treats its neighbours' sewage

The Airdrie–Calgary wastewater pipeline: a 7 km, $114 million line to Calgary's treatment system, plus how Calgary's regional wastewater servicing works.

7 min read
Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.